To schedule a report, click on the Reports tab and select the report you want to run from the available list on the left-hand side of the screen, as shown below:

Screenshotmacro
Borderfalse
URL/download/attachments/1540137/reports_on_demand_1.png

To change any of the report's parameters, refer to the relevant page(s) in the list below:

When you have configured these parameters, click on the Schedule button, as shown below:

Screenshotmacro
Borderfalse
URL/download/attachments/1540139/schedule_reports_1.png

A new window will open, where you can set the scheduling parameters of the report:

  • when you want the report to first run
  • how frequently you want the report to run
  • how you want the report delivered
  • who should receive the report

Screenshotmacro
Borderfalse
URL/download/attachments/1540139/schedule_panel_1.png